Drywall, texture, and paint

After the siding was finished, the gutters and gas meter were installed before painting.  At this point, all exterior painting is complete pending some touch-up work.

 

On the interior, all drywall work is complete with texture and first coat of paint on.  After next steps (cabinets and flooring), we’ll have another coat of paint to ensure good coverage and to capture any damage from the flooring/cabinet installation.

 

The driveway is being prepped for pouring and the yard has been prepped for sod and landscaping.  We met with the landscaper POC last week to discuss our plans for the yard.  I suspect we’ll have the driveway poured within a week and landscaping will follow a week after that.  This leaves us with finishing up the interior over the next four weeks — installing flooring, cabinets, counters, light fixtures, and the air conditioner.  We’re still on schedule.  Seeing as we’ll be moving from a small, single bedroom apartment, our next few weekends will be focused on appliance and furniture shopping.

Advertisements
Posted in Home Build

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Enter your email address to follow this blog and receive notifications of new posts by email.

Join 1,101 other followers

Instagram
Progress on the house... House foundation is complete.  Should be fast progress all summer. Why would you do that? Questionable home staging On top of the old @seattletimes building - "We want free wifi and $2 hoes"
#officeviews And from the other side...
Follow Pi Fun on WordPress.com
%d bloggers like this: